Pack Studio reduces every option to one figure: box, protective packaging, pallet and freight divided across the parts on board. Returnables add a break-even period.

Best for Comparing packaging options on true landed cost.

Packaging options ranked by real-time cost, rolling box, dunnage, pallet and freight into cost per part

Every option in Pack Studio is reduced to one figure: cost per part. That is what lets a taller box, a different orientation or a returnable rack be compared fairly.

The formula

Cost per part = (box + protective packaging + pallet + freight) ÷ parts on board

The lowest-cost option ranks first. Because freight is divided across the parts on board, a denser pack shows up directly as a lower cost per part.

Inputs

  • Packaging materials: priced from market pricing, with the corrugated board grade chosen to survive the pallet-stack load.
  • Freight: a cost per delivery plus a cost per mile. The published studies use $200 per delivery plus $2 per mile over 100 miles.
  • Weight and cube limits: set whether a truck fills by volume or by weight.

Return on investment (ROI) for returnables

For returnable fleets, the result is also expressed as a break-even period in months: how long until reuse savings repay the upfront cost of the fleet.

Why it matters

Purchasing often sees only the piece price. In one worked example from The Packaging Perspective Series, a supplier chosen for a 12-cent lower piece price turned a projected $42,000 annual saving into a $791,000 loss once logistics, packaging, warehousing and quality were counted.

Questions about Cost Per Part and ROI

What goes into cost per part?

The box, protective packaging, pallet and freight, summed and divided across the parts on board.

How is ROI shown for returnable packaging?

As a break-even period: the number of months until reuse savings repay the upfront cost of the fleet.

Articles on Cost Per Part and ROI

Sources for the figures on this page

  1. The Packaging Perspective Series: Landed Cost, Pack Studio, 2025-12-17. Net annual result of choosing the lowest piece price: a $791,000 loss.

Every figure resolves from the facts registry.

Machine viewWhat agents read

Loading…